ARMOR · Spring 2025

Production Control: Way to Prioritize Maintenance in Armor Battalions

LTC Michael D. Hebert, MAJ Grant P. Roberts, CW4 Wes Leach,
pp. 23–26Features2025

Article

Automatically extracted text. Reading order, article boundaries, and formatting may contain errors; compare with the original source scan.

Spring 2025 Production Control: Way to Prioritize Maintenance in Armor Battalion It is well known the National Training Center (NTC) can challenge and stress maintenance and sustainment systems. Following a rigorous training cycle 1st Battalion, 68th Armor Regiment left Fort Irwin with three of 29 tanks operational and zero of 18 Bradley fighting vehicles operational. It was late November and 3rd Armored Brigade Combat Team (ABCT) was scheduled to begin outload operations in January. In six working weeks, the battalion rebuilt the operational readiness (OR) rate to 79 percent and drove 37 of 47 combat platforms (under their own power) from the motor pool to the railhead. During the subsequent deployment to the U.S. European Command area of operations, the battalion maintained a readiness rate of 77 percent or better throughout the deployment. This statistic includes 30 days of Field Operations. This was despite a national (federal) budget funding deficit for the first quarter and being at the end of the supply line as a standalone battalion. After NTC Rotation 24-02 the battalion maintenance program needed some additional rigor. That rigor came in the form of a meeting observed in the adjacent aviation brigade: The production control meeting (PCM) and the plan methodology (problem, people, parts, time, tools, and training or P4T3). Production control, ABCT maintenance Maintenance is important in any formation, but it is especially vital in both aviation and armor units. For years, Army aviators have adhered to the P4T3 methodology to ensure their equipment is maintained to the highest standard. Prior to NTC, the concept of executing a PCM had been discussed inside the battalion. However, many ground units are reluctant to adopt the PCM, as it seems cumbersome and impossible to accomplish. One issue that arose is the difference between the amount of support personnel assigned to aviation units compared to those assigned to an armored unit. For example, assets available at the aviation squadron/battalion level differs from those of a combined arms battalion (CAB). If you ever sit in an aviation PCM, you’ll be surrounded by chief warrant officers, military occupational specialty (MOS) 92Y, Unit Supply Specialists; and field service representative (FSR) liaisons. On the other hand, a CAB has one maintenance warrant officer and limited habitual direct support from FSRs. And that’s okay. The PCM and P4T3 is still a framework that CABs can use to prioritize the assets you do have. The PCM was developed over time, after attending a few aviation PCM’s with the 6th Squadron, 17th Air Cavalry Regiment and using Army Techniques Publication (ATP) 3-04.7, Army Aviation Maintenance as a guide. The 1-68 Armor trained company executive officers (XOs) were to brief their status of equipment using the P4T3 model. Briefers were trained to cut to the point quicker by describing the P4T3 challenges directly as opposed to briefing all seven steps individually. There was a lot of maintenance to be done, with limited crews and mechanics to do it all. Over time, the PCM allowed a daily touch point for commander priorities, that provided troops to tasks, and job prioritization that previously had been overwhelming. The focus enabled field maintenance teams (FMTs) and the maintenance platoon to apply themselves to directed maintenance priorities based on parts, people, and tools available. The PCM also armed the battalion leadership with accurate projections for daily maintenance expectations. The PCM is now executed four days a week (Tuesday-Friday). This 30-minute or less meeting produces daily maintenance priorities and troops to tasks. This is now the most important meeting in the battalion and ensures the fleet receives the appropriate attention. Executing a PCM 30 minutes prior to the duty day, commanders (CDRs) or XOs brief planned jobs. Support shops/ sections back-brief planned jobs to confirm priority. This immediate feedback and direct coordination lead to an increase in OR rate, decreasing time equipment spent non-mission capable by roughly 30 percent across the battalion. The ability to address any of the seven areas in that meeting and alleviate issues allowed for a shared understanding and “ownership” of who would remedy the gaps in assets or support. This reduced the “3-foot wall” and helps operators and mechanics understand most issues could be resolved the same day. Overall, there is a better understanding in troubleshooting and maintenance actions directly correlating to increases in readiness. After a few months, the PCM could be conducted in as little as 20 minutes. The XOs sought maintenance resolution through cross talk, preventing issues from becoming larger problems and/or delays. With direct involvement and enforcement from the battalion command team, the companies were able to overcome hurdles and continue towards getting equipment ready to fight. The ability to conduct a quick, precise, and worthwhile meeting also allowed for the battalion command team to brief more accurate readiness pictures to higher by ensuring all obstacles were addressed and plans were in place to repair equipment as efficiently as possible. Production control meeting The PCM is chaired by the battalion CDR or XO. Companies are represented by LTC Michael D. Hebert, MAJ Grant

P. Roberts, CW4 Wes Leach, and CPT Colleen Talbott

Spring 2025 Agenda

ACTION

REPRESENTATIVE(S)

SUPPORT ACTION

Opening Comments

BN CDR, BN XO, BMT, BMO, MCO, MCS

Acknowledge Company Brief (in sequence specified at start) Slant Brief CO CDR or XO Acknowledge/record Bumper Number and Priority Plan: Problem, People, Parts, Time, Tools CO CDR or XO Provide People, Time, and Tools Repeat as necessary Support Back Brief Back brief, support requirements / priority, people, time, tools Base Maintenance Company Confirmation Back brief, support requirements / priority, people, time, tools S&R Company Confirmation Back brief, support requirements / priority, people, time, tools Armament Company Confirmation Back brief, support requirements / priority, people, time, tools Shop Office Company Confirmation Close Alibies Companies in sequence Acknowledge Supporting Elements Closing Comments

BN CDR, BN XO, BMT, BMO, MCO, MCS

Spring 2025 Figure 2. Plan Methodology (P4T3) Worksheet. (U.S. Army) Plan Methodology (P4T3) Worksheet “Plan” Brief Format Bumper Number: Company Priority: Nom: PL:

PSG:

Problem People 1 2 3 4 Supervisor/QAQC Parts

NSN

Part#

NOM

QTY

O/H 1 2 3 4 5 6 7 8 9 10 Time How much time is required to complete the maintenance action? Estimate: Is there sufficient time, free of distractions to affect the repair? Yes / No Remarks: Tools Special Tools: Additional Required Tools Plan Methodology (P4T3) “Plan” Brief Explained Complete admin data for reference and accountability Describe the problem. A maintenance event or problem must be identified. Identify the people for accountability. Maintenance managers will assess available resources who are adequately trained to conduct maintenance. Parts. Before performing maintenance, personnel should verify that they have the correct type and quantity of parts. Parts assessments are necessary to determine what is requred and available to correct deficiencies. If parts are not available a request for necessary parts/components must be processed immediately. Time. For the maintenance manager, time is critical to mission accomplishment. Maintenance managers must accurately evaluate time constraints when determining if there is sufficient time available for the action. Tools. Supervisors must identify the tools required to do a job and make sure they are on-hand, serviceable, and if required, calibrated. Leaders must educate themselves on different tools and enforce TM/TB standards. higher headquarters. If the plan is incomplete, additional resources must be provided before the job can be started. A complete plan means the job is ready to action. Strict adherence to the P4T3 briefing methodology is critical to keeping the meeting productive and concise. However, support elements/sections include in their back briefs an additional outline of jobs their subordinate teams are executing to ensure the whole team is used effectively. Example, Team 1 is supporting an Infantry Fighting Vehicle with an M88 Recovery Track, Team 2 is processing recoverable parts for turn in, and Team 3 is conducting annual services on two Light Track Vehicles. This shows us that Team 2 could be used more effectively on another job. This additional step helps drill down to the individual Soldier for troops to tasks and efficiency. Recommend adding that in as an additional step. Keep the companies to the P4T3 style briefing and shared sections brief P4T3 based on teams available. Conclusion The production control meeting is not exclusive to aviation formations. The PCM is widely applicable and can be used at the battalion and company levels to help organizations prioritize and manage maintenance programs. There is only one way to eat an elephant: one bite at a time. For the 1-68 Armor, the PCM allowed company FMTs to take small bites out of a major maintenance problem, and it established a means to manage jobs in a fast-paced ABCT operations tempo. The P4T3

Spring 2025 methodology provided a framework to brief maintenance priorities and confirm conditions are set prior to each duty day. Implementing these practices across the battalion enabled positive organizational change in maintenance and readiness. LTC Michael D. Hebert is the battalion commander of 1st Battalion, 68th Armor Regiment, 3rd Armored Brigade Combat Team, 4th Infantry Division, Fort Carson, CO (both at Fort Carson and Forward Operating Site, Nowa Deba Training Area, Poland). LTC He-bert’s previous assignments include aide de camp to the commanding general of Installation Management Command, Fort Sam Houston, TX; brigade XO, 3rdABCT, 1st Cavalry Division, Fort Cavazos, TX; squadron XO, 6th Squadron, 9th U.S. Cavalry Regiment, 3rd ABCT, 1st Cavalry Division, Camp Casey, Republic of Korea; and squadron operations officer; 6-9 Cavalry, 3rd ABCT, 1st Cavalry Division, Fort Cavazos. His military schools include U.S. Army Ranger Course, U.S. Army Airborne Course, Cavalry Leader Course and the Scout Leader Course, all at Fort Benning, GA. LTC Hebert has a bachelor’s of arts degree in communications from Louisiana State University and a master’s of arts degree in National Security and Strategic Studies from the Naval War College. MAJ Grant P. Roberts is the battalion operations officer, 1-68 Armor, 3rd ABCT, 4th Infantry Division, Fort Carson, CO. His previous assignments include battalion XO, 1-68 Armor, 3rd ABCT, 4thInfantry Division; aide-decamp, to the Supreme Allied Commander Europe / Commanding General, U.S. European Command, North Atlantic Treaty Organization (NATO) Headquarters, Belgium; company commander, Headquarters and Headquarters Company, 1stBattalion, 77th Amor Regiment, 3rd ABCT, 1st Armored Division, Fort Bliss, TX; and mechanized infantry company commander, 1st Battalion, 77th Amor Regiment, 3rd ABCT. MAJ Roberts’ military schools include U.S. Marine Corps Command and Staff College, Quantico, VA (2023); Joint Fire Power Course, Nellis Air Force Base (AFB), NV (2018); Bradley Commander Course, Fort Benning, GA (2017); Maneuver Captain’s Career Course, Fort Benning (2017); Basic Airborne School, Fort Benning (2014); Ranger School, Fort Benning (2014); and Infantry Basic Officer Leader Course, Fort Benning (2013). He has a bachelor’s of arts degree in political science from Miami University (2010). MAJ Roberts also has a master’s of arts degree in communications from Bellarmine University (2013) and a master’s of science degree in military studies from the Marine Corps University (2023). CW4 Wes Leach is a U.S. Army chief warrant ordanace officer currently serving as the battalion maintenance tech, 1-68 Armor, 3rd ABCT, 4th Infantry Division, Fort Carson, CO. His previous assignments include automotive warrant officer, 1-68 Armor; senior ordnance ground maintenance warrant officer, 1-2 Stryker Brigade Combat Team (SBCT); automotive warrant officer, 23rd Brigade Engineer Battalion, 1-2 SBCT; automotive warrant officer, 3rd Battalion, 13th Field Artillery Regiment; and automotive warrant officer, 709th Military Police Battalion. CW4 Leach’s military schools include Intermediate Level Education (formal education program for mid-career U.S. Army officers. It's a required part of the Command and General Staff Officer Course), Fort Rucker AL; Warrant Officer Advanced Course, Fort Gregg-Adams, VA. He has a bachelor’s of science degree from Embry Riddle Aeronautical University. CPT Colleen Talbott is the battalion maintenance officer, 1-68 Armor, 3rd ABCT, 4th Infantry Division. Fort Carson, CO. Her previous assignments include XO, 1st Battalion, 81st Armor Regiment; XO, 1st Battalion, 35th Armored Regiment; and tank platoon leader, 1-35 Armor. Her military schools include Armor Basic Officer Leader Course, Fort Benning, GA; Army Reconnaissance Course, Fort Benning; Maneuver Captain’s Career Course, Fort Benning; and Tank Commander Course, Fort Benning. CPT Talbott has a bachelor’s of science degree in biology from Radford University and master of social work degree in social work from Troy University. Notes 1 Chuck Brown, “P4T3 Supporting ‘Ready Now’ Maintenance” (Flightfax, 2019) https://safety.army.mil/Portals/0/Documents/ON-DUTY/AVIATION/FLIGHTFAX/ Standard/2019/Flightfax_78_June_2019. pdf. Acronym Quick-Scan ABCT – armored brigade combat team CAB – combined arms battalion CDR – commander FMT – field maintenance team FSR – field service representative P4T3 – problem, people, parts, time, tools, and training PCM – production control meeting NTC – National Training Center XO – executive officer “Sharing knowledge and experience is the greatest legacy that you can leave to subordinates.” - Chief of Staff of the Army GEN Carl E. Vuono (1987)

End of indexed article

Citation

LTC Michael D. Hebert, MAJ Grant P. Roberts, CW4 Wes Leach,. “Production Control: Way to Prioritize Maintenance in Armor Battalions.” ARMOR, Spring 2025, pp. 23-26.

Read deeper with Trackpads Books

Trackpads books turn research themes into longer narrative and reference works. Book purchases help support the project.

Explore Trackpads Books ↗

Listen to the history

Continue with Trackpads podcasts for military-history series, interviews, and narrated features.

Browse Trackpads Podcasts ↗